WiFi Expansion & Improvement Multi-Year Project - Fiscal Year 2016/17

The following list identifies areas on campus that have undergone upgrades of telecommunications cabling and replacement or installation of additional wireless access points (WAPs). 

This is a multi-year project. Learn about progress made in other years:

Fiscal Year 2013/14

Fiscal Year 2014/15

Fiscal Year 2015/16 

Fiscal Year 2017/18

Fiscal Year 2018/19

Fiscal Year 2019/20

Pending Waitlist

 

This list is in the order work is planned and will continue to be updated as scheduling may change and as work is completed.

*Areas with an asterisk received new WAPs (hardware) where WAPs may have already existed.

(Tip: To find a specific building, in most browsers you can use the “find” feature by simultaneously pressing Ctrl+F and typing in the building name. You can click the table column headings to sort in alphabetical or numerical order.)

Building Area Status
CPAC S-123, S-124, and S-125 Completed Fall 2016
Engineering Technology all workshop area Completed 11/2016
Engineering 3 all, except auxiliary Boeing Building Completed 10/2016
Engineering 4 all Completed 11/2016
Kinesiology rooms 51A/51B/58/59 Completed 12/2016
Facilities Corporate Yard - Design & Construction Services Entire suite Completed 01/2016
Facilities Management Eastern portion of building  Completed 01/2017
Academic Services 1st floor room 133 Completed 12/2016
MLSC* all Completed 11/2016
Microbiology* all Completed 11/2016
Academic Services* 2nd Floor  Completed 12/2016
Engineering Technology room 239 Pending (near future)
Engineering Technology 1st floor Pending (near future)
Engineering Technology  2nd floor Pending (near future)
Library 2nd and 3rd floors  Pending (near future)
Library 1st and Lower Level Pending (near future)
Studio Theater 1st   floor Pending (near future)
Studio Theater 2nd   floor Pending (near future)
Fine Arts 2 1st   floor Pending (near future)
Fine Arts 2 2nd   floor Pending (near future)
Peterson Hall 1 ALL   areas Pending (near future)
Engineering / Computer Science 3rd and   4th floor 3rd floor completed 10/2017 
Engineering / Computer Science 5th and   6th floor Pending (near future)
Fine Arts 3 1st   floor Pending (near future)
Fine Arts 3 2nd   floor Pending (near future)
Fine Arts 4 1st   floor Pending (near future)
Fine Arts 4 2nd   floor Pending (near future)
Faculty Office 4 1st   floor Pending (near future)
Faculty Office 4 2nd   floor Pending (near future)
Liberal Arts 1 1st   floor Pending (near future)
University Police   Pending (near future)