WiFi Expansion & Improvement Multi-Year Project - Fiscal Year 2014/15

The following list identifies areas on campus that have undergone upgrades of telecommunications cabling and installation of additional wireless access points (WAPs) beginning the week of January 27, 2014. 

This is a multi-year project. Learn about progress made in other years:

Fiscal Year 2013/14

Fiscal Year 2015/16 

Fiscal Year 2016/17

Fiscal Year 2017/18

Fiscal Year 2018/19

Fiscal Year 2019/20

Pending Waitlist

 

*Areas with an asterisk received updated WAPs (hardware) where WAPs already existed.

(Tip: To find a specific building, in most browsers you can use the “find” feature by simultaneously pressing Ctrl+F and typing in the building name. You can also use the table column headings to sort in alphabetical or numerical order.)

Building Area Start Date Status
Academic Services Entire Building 10/10/2014 completed 10/22/14*
Academic Services 3rd floor 3/10/2015 completed 3/20/2015
CBA Entire Building 9/22/2014 completed 9/24/14*
CPAC Lobby 4/20/2015 completed 4/23/2015
CPAC House Main Theater 10/24/2014 completed 10/24/14*
Design ALL areas 5/22/2015 completed 6/12/2015
Design ALL areas 6/19/2015 completed 7/2/2015
ECS Entire Building 10/7/2014 completed 10/27/14*
ED1 room 40 and 41 8/21/2014 completed 8/22/14*
ED2 room 158 8/22/2014 completed 8/22/14*
Engineering 2 1st and 2nd Floors 10/31/2014 completed 4/10/2015
Engineering 2 3rd floor 11/15/2014 completed Dec., 2014
Faculty Office 2 1st floor 2/10/2015 completed 2/18/2015
Faculty Office 2 2nd floor 2/11/2015 completed 2/18/2015
Faculty Office 3 Lower Level 2/18/2015 completed 2/19/2015
Faculty Office 5 1st floor 4/29/2015 completed 5/22/2015
Faculty Office 5 2nd floor 5/1/2015 completed 5/22/2015
Fine Arts 1 most areas 10/29/2014 completed 10/30/14*
Fine Arts 1 1st floor 2/23/2015 completed 3/17/2015
Fine Arts 1 2nd floor 2/23/2015 completed 3/17/2015
Fine Arts 2 most areas 10/29/2014 completed 11/26/14*
Fine Arts 3 most areas 10/29/2014 completed 11/26/14*
Fine Arts 4 classrooms 11/10/2014 completed 11/26/14*
Fine Arts 4 3rd floor 3/24/2015 completed 4/10/2015
HHS1 Entire Building 2/3/2015 completed 2/13/15
HHS1 2 classrooms rm 104 / rm 201 10/24/2014 completed 10/24/14*
HHS2 external offices 2/3/2015 completed 2/12/15
HSCI Entire Building 9/24/2014 completed 10/6/14*
LA1 2nd and 3rd floors 10/1/2014 completed 10/3/14*
Liberal Arts 1 2nd floor 2/19/2015 completed 6/10/2015
Liberal Arts 1 3rd floor 2/19/2015 completed 6/12/2015
Liberal Arts 2, 3, and 4 ALL areas   completed Jan., 2015
Liberal Arts 5 1st floor Jul-14 completed 8/5/14
Liberal Arts 5 2nd floor 7/31/2014 completed 8/22/14
Liberal Arts 5 3rd floor 7/31/2014 completed 8/22/14
Liberal Arts Building 2nd floor 4/16/2015 completed 5/1/2015
Liberal Arts Building 3rd floor 4/16/2015 completed 5/1/2015
Liberal Arts Building 1st floor 4/24/2015 completed 4/29/2015
Library 0, 1st, 2nd. And 3rd 10/13/2014 completed 10/17/14*
MLSC Entire Building 9/8/2014 completed 9/12/14*
Multi Media Center 1st and 2nd Floors 3/11/2015 completed 4/17/2015
Nursing rm 25, 22 10/29/2014 completed 10/29/14*
Psychology 1st and 2nd Floors 9/2/2014 completed 9/5/15*
Pyramid Fitness Complex 3/18/2015 completed 3/26/2015
Social Sciences / Public Affairs 3rd and 2nd floors 4/7/2015 completed 4/16/2015
Social Sciences / Public Affairs 1st floor 6/11/2015 completed 6/19/2015
University Music Center "A" Side A 5/4/2015 completed 5/20/2015
Vivian Engineering Center 1st floor ext rooms 12/15/2014 pending final testing