The following list identifies areas on campus that have undergone upgrades of telecommunications cabling and installation of additional wireless access points (WAPs) beginning the week of January 27, 2014.
This is a multi-year project. Learn about progress made in other years:
Fiscal Year 2013/14
Fiscal Year 2015/16
Fiscal Year 2016/17
Fiscal Year 2017/18
Fiscal Year 2018/19
Fiscal Year 2019/20
Pending Waitlist
*Areas with an asterisk received updated WAPs (hardware) where WAPs already existed.
(Tip: To find a specific building, in most browsers you can use the “find” feature by simultaneously pressing Ctrl+F and typing in the building name. You can also use the table column headings to sort in alphabetical or numerical order.)
Building |
Area |
Start Date |
Status |
Academic Services |
Entire Building |
10/10/2014 |
completed 10/22/14* |
Academic Services |
3rd floor |
3/10/2015 |
completed 3/20/2015 |
CBA |
Entire Building |
9/22/2014 |
completed 9/24/14* |
CPAC |
Lobby |
4/20/2015 |
completed 4/23/2015 |
CPAC House |
Main Theater |
10/24/2014 |
completed 10/24/14* |
Design |
ALL areas |
5/22/2015 |
completed 6/12/2015 |
Design |
ALL areas |
6/19/2015 |
completed 7/2/2015 |
ECS |
Entire Building |
10/7/2014 |
completed 10/27/14* |
ED1 |
room 40 and 41 |
8/21/2014 |
completed 8/22/14* |
ED2 |
room 158 |
8/22/2014 |
completed 8/22/14* |
Engineering 2 |
1st and 2nd Floors |
10/31/2014 |
completed 4/10/2015 |
Engineering 2 |
3rd floor |
11/15/2014 |
completed Dec., 2014 |
Faculty Office 2 |
1st floor |
2/10/2015 |
completed 2/18/2015 |
Faculty Office 2 |
2nd floor |
2/11/2015 |
completed 2/18/2015 |
Faculty Office 3 |
Lower Level |
2/18/2015 |
completed 2/19/2015 |
Faculty Office 5 |
1st floor |
4/29/2015 |
completed 5/22/2015 |
Faculty Office 5 |
2nd floor |
5/1/2015 |
completed 5/22/2015 |
Fine Arts 1 |
most areas |
10/29/2014 |
completed 10/30/14* |
Fine Arts 1 |
1st floor |
2/23/2015 |
completed 3/17/2015 |
Fine Arts 1 |
2nd floor |
2/23/2015 |
completed 3/17/2015 |
Fine Arts 2 |
most areas |
10/29/2014 |
completed 11/26/14* |
Fine Arts 3 |
most areas |
10/29/2014 |
completed 11/26/14* |
Fine Arts 4 |
classrooms |
11/10/2014 |
completed 11/26/14* |
Fine Arts 4 |
3rd floor |
3/24/2015 |
completed 4/10/2015 |
HHS1 |
Entire Building |
2/3/2015 |
completed 2/13/15 |
HHS1 2 classrooms |
rm 104 / rm 201 |
10/24/2014 |
completed 10/24/14* |
HHS2 |
external offices |
2/3/2015 |
completed 2/12/15 |
HSCI |
Entire Building |
9/24/2014 |
completed 10/6/14* |
LA1 |
2nd and 3rd floors |
10/1/2014 |
completed 10/3/14* |
Liberal Arts 1 |
2nd floor |
2/19/2015 |
completed 6/10/2015 |
Liberal Arts 1 |
3rd floor |
2/19/2015 |
completed 6/12/2015 |
Liberal Arts 2, 3, and 4 |
ALL areas |
|
completed Jan., 2015 |
Liberal Arts 5 |
1st floor |
Jul-14 |
completed 8/5/14 |
Liberal Arts 5 |
2nd floor |
7/31/2014 |
completed 8/22/14 |
Liberal Arts 5 |
3rd floor |
7/31/2014 |
completed 8/22/14 |
Liberal Arts Building |
2nd floor |
4/16/2015 |
completed 5/1/2015 |
Liberal Arts Building |
3rd floor |
4/16/2015 |
completed 5/1/2015 |
Liberal Arts Building |
1st floor |
4/24/2015 |
completed 4/29/2015 |
Library |
0, 1st, 2nd. And 3rd |
10/13/2014 |
completed 10/17/14* |
MLSC |
Entire Building |
9/8/2014 |
completed 9/12/14* |
Multi Media Center |
1st and 2nd Floors |
3/11/2015 |
completed 4/17/2015 |
Nursing |
rm 25, 22 |
10/29/2014 |
completed 10/29/14* |
Psychology |
1st and 2nd Floors |
9/2/2014 |
completed 9/5/15* |
Pyramid |
Fitness Complex |
3/18/2015 |
completed 3/26/2015 |
Social Sciences / Public Affairs |
3rd and 2nd floors |
4/7/2015 |
completed 4/16/2015 |
Social Sciences / Public Affairs |
1st floor |
6/11/2015 |
completed 6/19/2015 |
University Music Center "A" |
Side A |
5/4/2015 |
completed 5/20/2015 |
Vivian Engineering Center |
1st floor ext rooms |
12/15/2014 |
pending final testing |